A lot of Progress on the House

DSC00881 (Medium).JPGThere has been a lot of progress in the house over the last 2 weeks.

Last time I had posted they had just completed the texture of the drywall (click the pic for full-size).

Well during the last 2 weeks all of this has been completed -

  • Walls Painted
  • Base boards, trim, and window sills added
  • Kitchen and bathroom cabinets installed
  • All faucets and toilets installed
  • Bathroom showers, tubs, and tile installed
  • Bathroom towel and toilet paper fixtures
  • Air conditioning / heater unit installed
  • All switched, outlets, and light fixtures
  • Kitchen counter and tile back splash
  • Floor tile in the Kitchen, closets, entryway, and bathrooms
  • Closet and pantry wire shelves
  • Outside brick has been started

Wow, that is a long list. I did not even realize how much had been done until adding it here.

Things that still need to be completed are the brick on the outside of the house, actually hooking up the electrical, the carpet, fence around the yard, and landscaping.

The foreman has let us know that our first walk through will be May 2nd and we are expected to have the keys on May 12th.

It is really exciting to see all the progress.